It was not the first time I got this error message when trying to analyze results on LoadRunner Analysis. This is pretty strange since from the controller the test seemed to run fine. Usually I would just discard the test results and re-run it, just to avoid troubleshooting another problem caused by a LoadRunner bug that probably messed the results, but this time I decided to take some time to just check what was happened to the results.
When I tried to analyze raw results on Analysis, the import process fails and the error log has the following message:
Analysis Error log: <1 1:23:52="" pm="">
Error 75012: in file 25983.lrr the Stop_time is 0
This seems really strange, but first thing I tried was to open the .lrr file with a text editor. Searched for the Stop_time parameter and apparently it was missing. Start_time was there and apparently with the correct test start time. Let’s try to include Stop_time to the file and see what happens.
Both Start_time and Stop_time are Epoch, or UNIX time, which is pretty much seconds since 01-01-1970. Just to be sure, check your Start_time with a converter like . If the time is correct, do the math to check how many seconds your test ran. For example, 1 hour equals to 3600 seconds, 2 hours 7200 and so on.
Take this number and sum it with Start_time. Add a new parameter called Stop_time and use the result of your sum. Eg.:
Start_time=1325809089 // Fri, 06 Jan 2012 00:18:09 GMT
Stop_time=1325816289 // Fri, 06 Jan 2012 02:18:09 GMT
Saved the file and tried to open the results again and it worked
When I tried to analyze raw results on Analysis, the import process fails and the error log has the following message:
Analysis Error log: <1 1:23:52="" pm="">
Error 75012: in file 25983.lrr the Stop_time is 0
This seems really strange, but first thing I tried was to open the .lrr file with a text editor. Searched for the Stop_time parameter and apparently it was missing. Start_time was there and apparently with the correct test start time. Let’s try to include Stop_time to the file and see what happens.
Both Start_time and Stop_time are Epoch, or UNIX time, which is pretty much seconds since 01-01-1970. Just to be sure, check your Start_time with a converter like . If the time is correct, do the math to check how many seconds your test ran. For example, 1 hour equals to 3600 seconds, 2 hours 7200 and so on.
Take this number and sum it with Start_time. Add a new parameter called Stop_time and use the result of your sum. Eg.:
Start_time=1325809089 // Fri, 06 Jan 2012 00:18:09 GMT
Stop_time=1325816289 // Fri, 06 Jan 2012 02:18:09 GMT
Saved the file and tried to open the results again and it worked
LoadRunner Training in Bangalore
LoadRunner Training in Hyderabad
LoadRunner Online Training
LoadRunner Training in BTM
LoadRunner Training in Marathahalli
Best LoadRunner Training Institutes in Bangalore
Best LoadRunner Training Institutes in India
Training Institutes in Bangalorea
No comments:
Post a Comment